Ground Fixed Cadenza
Installation Instructions:

1. Attach the steel legs to the base of the instrument with the M8 NylocNuts and 2 part security caps. (1.1) (See Assembly Guide).
2. Attach Ground Fixing posts to legs (1.2) (See Ground Fix Post Installation Sheet)
3. Excavate 1 hole for the Steel legs 250mm diameter by 400-550mm deep depending on Key stage, in desired location upon decision from customer.
4. Locate (lower) legs into holes making sure they are vertical and level prior to concreting in place.
5. Once happy with location of the Instrument, fill holes using rapid hardening concrete. Be sure to compact concrete around legs and leave to dry according to manufactures guidelines.
6. Attach the 1 pair of beater to the saddle strap on the leg. (1.3).

Components:
M8 Nyloc Nut x4
M6x20 Security Screw x2
2 Part Cover Cap x4
M6 Saddle Strap x1
Pair Small Red Beaters x1

Ground Fix Components:
M10x200 Bolt x2
M10 Nut x4
Assembly Guide: Components List

2 Part Cover Cap X4
M10 Nut X4
M10x200 Threaded Bar X2
Saddle Strap X1
M6x20 Pin torx X2
M8 Nyloc nut X4

Thread Lock Solution Required (not supplied).
Ground Fix Post Installation

1. Insert M10x 150 Threaded bar into pre drilled holes in Ground Fixing Post.
2. Fix M10x 200 Threaded bar in place using M10 Nuts.
3. Excavate 6 holes with a 250mm diameter tapering down to 350mm diameter and 450mm depth.
4. Compact base of hole with 50mm of aggregate. Lower ground Fix post attached to instrument into hole (check instrument straight and level before filling with concrete).
5. Fix hole with fast drying concrete to manufacturers specifications.